Driveway
This project was a new driveway and walkway. The previous driveway was cracked and worn; in need of removal. We hammered out the old driveway which was placed on pea gravel and had no rebar. The pea gravel was removed. New 3/4″ crushed gravel was installed and compacted. Rebar was then installed on a 2′ grid pattern. New concrete was then poured and broom finished.